Earned Value Management (EVM) Simulator
Earned Value Management (EVM) Simulator
Created By : Ir. MD Nursyazwi
Visualize and analyze project performance using key EVM metrics in real-time.
How to Use This Simulator
This tool helps you understand Earned Value Management by calculating and charting project health based on three key values:
- Planned Value (PV): The work you planned to have completed by a specific point in time. It's the budget for the work that was scheduled.
- Earned Value (EV): The value of the work you have actually completed. It's the budget for the work that has been performed.
- Actual Cost (AC): The actual money you have spent so far on the project.
Use the sliders in the Data Input section to set your project's initial budget, total duration, and your current progress (work performed and actual costs). The new Performance Variation (%) slider introduces a random fluctuation to the earned value and actual cost, simulating real-world project uncertainty. The simulator will then display a comprehensive set of performance metrics and a visual chart to help you instantly understand the project's status.
Data Input
Adjust the sliders below to set the project parameters and simulate its performance.
EVM Metrics & Results
EVM Performance Chart
The Science of Earned Value Management
Earned Value Management (EVM) is a project control methodology that integrates project scope, schedule, and cost data to provide an objective measure of project performance. The following metrics are fundamental to EVM.
- Budget at Completion (BAC): The total planned budget for the entire project. This is the baseline value against which all performance is measured.
- Planned Value (PV): The budgeted cost for the work scheduled to be completed by a given point in time. It is calculated as: PV = BAC * (Current Time / Total Duration).
- Earned Value (EV): The budgeted cost for the work actually completed. It is a direct measure of the work performed, independent of cost. It is calculated as: EV = BAC * (Work Performed Percentage).
- Actual Cost (AC): The total cost incurred for the work performed up to a given point in time. It is calculated as: AC = BAC * (Actual Cost Incurred Percentage).
Performance Metrics
These metrics quantify the variance of the project's performance from its plan at the current time.
Schedule Variance (SV) = EV - PV
Indices provide a ratio-based view of performance, where a value greater than 1.0 is favorable.
Schedule Performance Index (SPI) = EV / PV
Forecasting Metrics
These metrics forecast the final cost and schedule of the project based on current performance trends.
Estimate to Complete (ETC) = EAC - AC
Variance at Completion (VAC) = BAC - EAC
References & Further Reading
To learn more about Earned Value Management, you can consult these reputable sources:
Other Simulators
Explore other interactive tools to help with project management and business analysis:
- Quality Cost Simulator: Optimize your project's quality.
- Advanced Cost of Quality Model Generator: Create a detailed model to analyze quality-related expenses.
- Advanced CPM Simulator: Plan and manage project schedules using the Critical Path Method.
- Advanced PERT Simulator: Estimate project durations and visualize uncertainty.
- Advanced WBS Simulator: Structure your project scope with a work breakdown structure.
I'm so impressed with this EVM tool! It brilliantly simplifies a complex topic and provides a clear picture of a project's health. A fantastic resource for students and professionals alike! #EarnedValueManagement #PMBOK #ProjectLife #ConstructionManagement #Efficiency
ReplyDeleteElevate your project management game! This EVM simulator offers a clear, visual way to analyze cost and schedule variances. A fantastic tool to add to your arsenal.
ReplyDeleteThis is such a useful and well-designed tool! The EVM Simulator is a fantastic way to explore the relationship between project cost, schedule, and scope. A huge thanks for creating such an educational and inspiring resource.
ReplyDelete#EVM #ProjectManagement #Planning #PMI #ProjectLifeCycle
What a stellar resource for applied project management! The simulator's clear definitions of key metrics and its visual representation of project health provide a comprehensive learning experience. It's an indispensable tool for bridging the gap between theoretical knowledge and practical application. #AppliedScience #ProjectSuccess #EVMsimulator #BusinessEducation
ReplyDeleteThank you for creating and sharing this simulator. It's an invaluable tool for both professionals and students who need to grasp the core principles of earned value management in a practical way. The positive user feedback in the comments section is well-deserved. #ProjectManagementTools #CostControl #ScheduleManagement #ResourceManagement #EducationalResource
ReplyDeleteReal-World Project Simulation! 🛠️ Ir. MD Nursyazwi's EVM simulator is brilliant. It lets you simulate real-world uncertainty with a performance variation slider, giving you a deeper understanding of how to manage costs and schedules effectively. #BusinessTools #EarnedValue
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteJust checked out this EVM simulator! It's so helpful to see the relationship between Planned Value, Earned Value, and Actual Cost. What are some of your favorite project management tools or techniques for keeping a project on budget and on schedule? Let's discuss! #ProjectPlanning #EVM #PMO
ReplyDelete